Phase I of Facade Repairs for Fairlington Towne Condominium
Posted on Nov 17th, 2026
KGS is planning to begin the façade work at Fairlington Towne Condominium for the chimneys in the next few weeks and we wanted to reach out and share information with the community regarding what to expect. Please review the information below for additional details regarding the next steps.
Schedule
- Start date: Monday, November 30, 2026, beginning with a mock-up at Building 1 (3700 King St).
- Duration: 126 calendar days (approximately early April 2027, weather and conditions permitting).
- Work areas: KGS will work on 2–4 buildings at a time. A building-by-building schedule is available below along with a map. The map can also be downloaded and viewed as a PDF by clicking here.
- Hours: 8:00 AM to 5:00 PM. Noisy work will not begin before 9:00 AM.
- Weekends: Weekend work is rarely planned. It will occur only if needed for makeup work or unforeseen issues.
Phase 1 Fairlington Towne
(Chimney Repairs, First Round)
Mobilize: 11/30/26 -12/01/2026 – set up staging area and protection at Bldg.1
12/01-12/04: Bldg.1 (2 chimneys for mock up)
12/03-12/10: Bldgs. 2-3-4 (9 chimneys)
12/11-12-18: Bldgs. 5-6-7 (9 chimneys)
12/18-12/23: Bldgs. 8-9 (7 chimneys)
12/24-12/25: NO WORK FOR HOLIDAY
12/28-12/31: Bldgs.10-11 (7chimneys)
01/01/2027: NO WORK FOR HOLIDAY
01/04-01/08: Bldgs.12-13-14 (10 chimneys)
01/08-01/15: Bldgs.15-16-17 (10 chimneys)
01/15-01/22: Bldgs.18-19-20 (10 chimney)

Back Gate and Backyard Access
- KGS needs access to the back gates at each building where work is under way. Please make sure gates are unlocked and accessible when asked and based on the building-by-building schedule.
- Please stay out of backyards during work hours (8:00 AM–5:00 PM) in work areas.
Dust and Debris, Noise
- KGS will protect roofs, clear debris from gutters and downspouts, and clean backyards. Equipment will use HEPA filtration to reduce dust.
- Please keep windows and doors closed and locked during work hours to keep dust out of your home while they are working on your building.
- If you notice excessive dust or debris anywhere, including coming down your chimney, please contact Austin Figueroa, Portfolio Manager, at austin.figueroa@fsresidential.com as soon as it is observed.
- KGS will use generators to power their equipment. These can be loud, especially if they are stored right outside of windows/doors.
Chimneys
- Chimneys cannot be blocked because they vent resident HVAC systems. KGS will temporarily install a one-way damper that lets exhaust gases out but keeps dust and debris from coming in.
Interior Inspections and Leaks
- KGS will not be inspecting unit interiors.
- Please report any active leaks to Austin Figueroa, Portfolio Manager, at austin.figueroa@fsresidential.com to have these resolved outside of this planned project.
Crew and Parking
- The crew of approximately 7 will wear safety vests and hard hats for identification.
- A map showing the locations of parking and expectations of where they will be located is available below for review that are circled I red. These areas will be marked off when KGS begins their work and signs placed advising these spaces are reserved and take up 3-4 spaces in total. In the event owners are found parked in these parking spaces, then the Association will have the vehicles towed and relocated to an open parking space nearby.

Thank you for your patience as we complete this important work.